Camyr Allyn Stage 2

  • Stage 2 at Camyr Allyn is expected to register in the coming weeks.

Vacy Village

Current Registration Estimate: Q1, 2024.

  • Civil works are nearing completion at Vacy Village.
  • Hunter Water clearance has been obtained.
  • The electrical design has been approved for Stage 1 and the contractor engaged to commence works shorty.
  • Upcoming efforts will focus on finalising remaining electrical design for Stages 2 and 3, electrical works and landscaping.

Vacy Acres Stage 4

  • DA modification approval in line with original consent (14/03/23)
  • Preparation of documentation for lodgement of subdivision works certificate (SWC) application is nearing completion.
  • Once lodged, we expect Council's SWC approval process to take around 10 weeks.